2003-03-18

NPM 005-2003

Requesting Entity: National Power Corporation

Issues Concern: Additional Oil-based Fuel Requirements of NPC its IPPS and SPUG Power Barges for CY 2003

 

Details

Since the submission and completeness of the NFCC is imperative and vital for the prospective bidder’s eligibility, it cannot be waived. However, in the interest of public service, economy and efficiency, an agency may adopt the alternative methods of procurement provided in Section 35 of the IRR of E.O. 40, whenever justified by extraordinary circumstances provided therefore.